The process problem that reaches the management meeting is usually three weeks old. By the time it has a slide, it also has a customer's name on it, a delivery date that was missed and someone who has to explain. Yet almost everyone upstream saw a smaller version of it earlier: a queue that had grown, a colleague asking whether anyone had heard back from technical clearance, a spreadsheet that quietly gained a column called "urgent".
Those early signs are rarely hidden. They are simply not connected to anyone who is expected to act on them. Operational teams are busy with today's cases, management sees monthly numbers, and in between there is no mechanism that turns "this looks a bit off" into "someone is looking at it". This edition of Quick Tips is about five practical ways to notice process problems while they are still small enough to fix without a crisis.
Take the spare-parts order process at a mid-sized machinery manufacturer. Over five months the lead time from order receipt to shipment crept from four days to nine. Nobody noticed, because the monthly report showed an average that moved by a day at a time, and a one-day change never looks alarming. What actually happened was concentrated in one step. The technical clearance queue, which checks whether a replacement part matches the installed machine, grew from about twenty open items to more than 140. The engineer doing the work was covering for a colleague on parental leave and had been raising it, verbally, for weeks.
The escalation came when a key customer's production line stood still for two days waiting for a part that had been sitting in that queue. Within 48 hours the queue was cleared with help from two other engineers and the lead time fell back to five days. The fix was easy. It was applied four months late, and those months cost a customer relationship and several thousand euros in expedited shipping.
The structural problem here is not that people were careless. The company measured the process at the wrong level (an average across all orders, reported monthly) and at the wrong distance from the work. The signal that mattered, the size and age of one queue, was known to exactly one person, and that person had no channel for it other than mentioning it in passing. In many organisations the only reliable channel for a process problem is escalation, which by definition happens after the damage. The five tips below are about building a cheaper channel.
Averages are late by construction. A lead time averaged over a month and reported in the following month tells you about work that started up to eight weeks ago. Queues are early. The number of open items in front of a step, and the age of the oldest one, change the day the problem starts.
For each step in a core process that has a handover before it, record two numbers once a day: how many items are waiting and how long the oldest has been waiting. In most ERP, ticketing or workflow systems this is a saved filter, not a project. The point is to see the number every day, in the same place, so that a doubling over three weeks is visible as a trend rather than as a surprise.
The machinery company now has exactly this: a short list of six queues, each with a count and an oldest-item age, visible to the team leads every morning. The technical clearance queue went from 140 to a steady 25, and when it crossed 40 in the summer holiday period, the lead noticed on day two, not month four.
Ask yourself: for the step in your core process that most often causes delays, do you know today how many items are waiting there and how old the oldest one is, or would you have to ask someone?
A number on its own is not a signal. Forty items in a queue is a crisis in one team and a quiet Tuesday in another. What turns a number into an early warning is an agreed idea of what normal looks like for that step, and a boundary beyond which someone takes a look.
The useful format is a range, not a target. A target invites gaming and arguments about whether it is fair. A range says: between ten and thirty open items, this step runs fine; above thirty, the team lead checks why; above sixty, it goes to the weekly operations meeting. The thresholds do not have to be precise. They have to exist, be written down, and be known by the people who see the numbers.
Set them from history where you can. Look at the last six months and ask what the queue looked like in the weeks when the process ran well. That is your normal range. If you have no history, start with a guess, run it for a month, and adjust. A threshold that is wrong by twenty percent is far more useful than no threshold, because it forces the conversation about what the step can actually absorb. This builds directly on the idea in our earlier piece on moving from reporting to process improvement: a metric only helps if it is tied to an action.
Ask yourself: if the queue in front of your slowest step doubled next week, is there a written number that would make someone react, or would it depend on who happened to notice?
Queues and thresholds catch problems that show up as volume. Many problems do not. A process can run at normal speed while the share of cases that take a detour quietly rises: a rework loop between two teams, a growing number of orders that go back to sales for clarification, an exception path that was meant for five percent of cases and now carries a quarter of them. The dashboard shows the same lead time it always has, because the detours are absorbed by people working harder.
This is where process mining earns its place. Because it reconstructs the actual path of every case from system timestamps, it shows drift that no single metric was designed to capture: the frequency of each variant over time, where waiting time between steps is growing, which loops are appearing. A rework loop that doubles its share over a quarter is one of the most reliable early signals there is, and it is invisible in a KPI report. Platforms built for the mid-market, noreja among them, make this a recurring view rather than a one-off analysis.
The practical habit is a monthly comparison of the executed process against the previous month: which paths grew, which shrank, where did the waiting time move. Twenty minutes, one view, the same questions every time.
Ask yourself: if the share of cases taking a detour through rework had doubled over the last quarter, would any report you currently receive show it?
A signal nobody owns is noise. The engineer at the machinery company had the information; what was missing was anyone whose job it was to receive it. For each early warning you define, write down three things: who looks when it fires, how quickly, and what they are allowed to do about it.
The third part matters most. If the only option available to the person who sees the signal is to escalate, you have recreated the original problem with an earlier timestamp. The first response should be something they can do on their own authority: redistribute work for a week, pause a low-priority intake, pull in a named colleague for two days, or decide that the signal is a false alarm and note why. Escalation stays available, but as a second step, not the first. Our piece on escalation as the default way to get things done describes what happens when it is the only step.
Keep the response short. A fifteen-minute look within one working day is enough in most cases, because at that stage the problem is still small. What the early signal buys you is cheap options; let people use them.
Ask yourself: for the last process problem that escalated in your organisation, who would have been the right person to look at it a month earlier, and did that person have any authority to act?
Every process produces cases that almost went wrong. The order that was rescued by a phone call, the invoice that someone caught the day before the deadline, the customer who was kept calm by an account manager who happened to check. These near-misses are the richest early warning source most companies have, and almost none of them record it, because nothing bad happened.
Make them visible with the lightest possible mechanism. A shared list, a tag in the ticketing system, a standing question in the weekly team meeting: which cases this week only worked because someone intervened? Collect them for a month and patterns appear quickly. Three near-misses at the same step are a process problem that has not yet escalated, and that is exactly the moment to fix it. The way the organisation handles these cases also tells you a great deal about where the standard path no longer fits, a theme we looked at in handling exceptions without breaking flow.
The important rule is that reporting a near-miss must never cost the person who reports it. If the response to "I had to call the warehouse directly to get this out" is a discussion about following the process, the list will be empty within two weeks. The response should be thanks, and a question: what would have had to be different for the call not to be necessary?
Ask yourself: do you know which three cases in your core process came closest to failing last month, and what they had in common?
Which of your current process metrics would have shown the last escalation a month before it happened, and which only confirmed it afterwards? Who in your organisation sees the queues every day, and what happens when they say something is building up? How many of the problems that reached your management meeting this year were genuinely sudden, and how many had been visible to someone for weeks? If a rework loop in your core process doubled in share over a quarter, how would you find out? And what does it say about your process if the only reliable way to get attention for a problem is for a customer to notice it first?
Process problems rarely arrive without warning. They arrive without a listener. The queue grows, the detours multiply, the near-misses pile up, and all of it is visible to someone who has no channel and no authority to act. The escalation that follows is the predictable result of measuring the process at the wrong level and from too far away.
The five tips move the listening closer to the work: watch queues instead of averages, agree what normal looks like, look at the executed process for drift, give each signal an owner with real options, and collect the cases that almost went wrong. None of it needs a project. Most of it needs a saved filter, a written threshold and a standing question in a weekly meeting.
A practical start: pick the one step in your core process that has caused the most escalations in the last year, find out how many items are waiting there right now and how old the oldest is, and write down the number above which someone should take a look. That takes an afternoon, and it is usually where the next escalation would have started.
Measure the process close to the work and often: the number of open items in front of each step and the age of the oldest one, checked daily, show a problem weeks before a monthly average does. Add agreed thresholds, an owner for each signal and a regular look at the executed process to catch drift that volume metrics miss.
Growing queues in front of one step, a rising age of the oldest open item, an increasing share of cases taking a rework or clarification loop, longer waiting times between handovers, and a growing number of cases that only succeed because someone intervened. Each of these appears well before lead time or customer complaints move.
Because they are aggregated and delayed. A monthly average over all cases moves slowly even when one step is in trouble, and it is reported weeks after the work happened. By the time an average looks alarming, the underlying problem has usually existed for months.
Process mining reconstructs the actual path of every case from system data, so it shows changes that no single metric captures: variants growing in share, rework loops appearing, waiting time shifting between steps. Comparing one month's executed process with the previous one makes drift visible before it turns into delays.
A named person takes a short look within a working day and has options they can use on their own authority, such as redistributing work or pausing low-priority intake. Escalation remains available as a second step. If the only possible response is escalation, the signal has not changed anything except the timestamp.